Answer:
Option C
Explanation:
Set a = the rate of A in (piece of work)/day
b = the rate of B in (piece of work)/day
c = the rate of C in (piece of work)/day
Below is the equation for all three working together.
($10$ days )$\times$ $(a+b+c)$ = 1(piece of work)
Next we have the equation were all work together for 4 days,
then only B and C continue for $10$ more days.
($4$ days) $\times$ $(a+b+c )$ + ($10$ days)$( b + c)$ = 1(piece of work)
Since each left hand side is equal to 1 piece of work,
we have
($10$ days) $\times$ $( a + b + c )$ = ($4$ days) $\times$ $(a+b+c)$ + ($10$ days)$(b+c)$
and
$10(a+b+c )$ $= 4(a+b+c )$ + $10(b+c)$
$10a + 10b + 10c$ $= 4a + 4b + 4c + 10b + 10c$
combining terms
$10a+10b+10c$ $=4a+14b+14c$
Notice that we can rewrite the above as
$10a + 10(b + c)$ $=4a+4(b+c)$
if we subtract $10(b + c)$ from each side
$10a$ $=4a+4(b+c)$
subtract $4a$ from each side
$6a$ $= 4(b + c)$
divide each side by $4$
$\frac{6a}{4}$ $=(b+c)$
Recall
($10$ days) $\times$ $(a+b+c)$ = 1(piece of work) or
$10(a+b+c)$ $= 1$
So
$10a+10(b+c)$ $=1$
Now substitute $\frac{6a}{4}$ for $(b+c)$ and we have
$10a + 10\left(\frac{6a}{4}\right)$ $= 1$
$10a+15a$ $= 1$
$25a=1$
This means that A at rate a will take 25 days to complete the work.